Construction to replace a water main near Bldg. 201 begins Thursday, Dec. 8, 2016, and will last for approximately four weeks. During this time, there will be intermittent partial road closures of Inner Circle Drive between Meridian and Northgate Road. Sidewalks may be closed during parts of the construction.
The contractor will start digging test holes to locate utlities and installing tree protection measures on Thursday, Dec. 8. Trenching operations are expected to begin Monday, Dec. 19. The project will involve digging up the old, leaky 8-inch ductile iron canal water main and replacing it with a new 8-inch HDPE canal water main. Flaggers, signage and other safety measures will be implemented during road closures.
Watch for more information in the coming weeks.